- 실적자료분석(實績資料分析)에 의(依)한 일정계획(日程計劃)
- ㆍ 저자명
- 김동찬,김우식,Kim. Dong-Chan,Kim. U-Sik
- ㆍ 간행물명
- 대한산업공학회지
- ㆍ 권/호정보
- 1978년|4권 2호|pp.59-66 (8 pages)
- ㆍ 발행정보
- 대한산업공학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
This paper is a work scheduling for design of piping Department of chemical plant using accumulated curve. Accumulated curve prepared by analysis of performance data, collected executed manhours for chemical plant of "D" Company during the past two years. It compared scheduled manhours with actual used manhours up to six months, put into the form of figures and charts the results can he summarized as below; 1) It can he found an important factor of critical control thus piping department got 30% of total scheduled menhours. 2) A plan of manpower mobilization can be scheduled before work starting. 3) Project progress can he found easily as put into the form of figures and charts for schedule to actual.