- 부하평준화 휴리스틱을 이용한 선박 탑재 일정계획 편성 연구
- ㆍ 저자명
- 백태현,정귀훈,박주철,Baek. Tae-Hyun,Chung. Kuy-Hoon,Park. Ju-Chull
- ㆍ 간행물명
- 산업공학
- ㆍ 권/호정보
- 1999년|12권 3호|pp.354-361 (8 pages)
- ㆍ 발행정보
- 대한산업공학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
In this paper, resource leveling heuristics are developed for ship erection scheduling. The heuristics, which enable scheduling with limited resources, are composed of the gradual resource limit decrease anti the resource allocation. At first, earliest start(ES) schedule is derived by PERT to get initial resource limit. And then, the heuristics lower the resource limits by a given increment and derive a new schedule from day-by-day resource allocation procedure. The procedure is repeated until the project duration reaches at the given ship erection duration, called dock cycle. Through the application of the heuristics for real world ship erection projects, wc can observe significant improvement in resource leveling.