- 공정 교체 시간을 고려한 배치작업의 일정계획
- ㆍ 저자명
- 김주일,이영훈
- ㆍ 간행물명
- 韓國經營科學會誌
- ㆍ 권/호정보
- 2001년|26권 2호|pp.69-83 (15 pages)
- ㆍ 발행정보
- 한국경영과학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
The problem of minimizing total tardiness on a batch processing machine with incompatible job families when there are sequence independent setup times between families is studied where all jobs of the same family have identical processing times and jobs of different families cannot be processed together. A batch processing machine can process a number of jobs, within a maximal batch size, simultaneously as a batch. The processing time required of each batch is equal to the one of jobs. A dynamic programming algorithm which gives the optimal solution, and several heuristics are presented. Performance of simple dispatching rules based on due dates are compared, and the best of them is used as an initial solution for the decomposition algorithm, which is shown to give good schedules in relatively short computational time.