- 중수로형(重水爐形) 원자로 건물의 Open Top시공공법
- The Open Top Construction Method for the PHWR Reactor Building
- ㆍ 저자명
- 이수득
- ㆍ 간행물명
- 技術士
- ㆍ 권/호정보
- 2001년|34권 3호|pp.41-45 (5 pages)
- ㆍ 발행정보
- 한국기술사회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
이 논문은 한국과학기술정보연구원과 논문 연계를 통해 무료로 제공되는 원문입니다.
The nuclear power plant(NPP) construction is a mammoth project, which requires a huge construction budget and the long construction duration of about 7 years. Recently there is a trend to shorten the construction period, to save the construction cost and to ensure the competitiveness through adopting the open top construction method. In this method, the major equipment are moved into the building through its top, and the internal works of the reactor building are being in process without installation of a dome roof.