- 조선시대 화성성역의 공정관리 사례분석
- ㆍ 저자명
- 김균태,Kim. Kyoon-Tai
- ㆍ 간행물명
- 한국건축시공학회지
- ㆍ 권/호정보
- 2008년|8권 6호|pp.139-145 (7 pages)
- ㆍ 발행정보
- 한국건축시공학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
The objective of this paper is to analyze the construction management capacity of Choseon Dynasty and suggest a new interpretation on the construction capacity of the time management by reviewing the time management case during a representative construction project, HwaSungk construction project implemented in the latter period of Choseon Dynasty around 200 years ago. which was described in HwaSungSungYoukEuGye. The analysis results of the time management capacity during the latter period of Choseon Dynasty depicted in the HwaSungSungYoukEuGye is summarized as follows: (1) It took 2 years and 6 months to complete the Hwasung construction project. However, all of the single buildings were constructed within 6 months, a relatively short period of time. Judging from the fact, it can be assumed that the construction techniques using wood of the time were very sophisticated. (2) When the HwaSung was constructed, it took a relatively short period of time to complete works from placing the foundation to erecting columns and to placing a crossbeam on the columns. Based on the fact, it can be also inferred that assembly processing techniques of the time were also sophisticated and the level of member processing and assembling techniques of the time was considerably good as well. (3) The HwaSung construction was continued throughout the year without any influence by weather conditions, which tells us that division of labor by work was performed, and it was possible to mobilize labor force for the construction project even during the busy farming seasons.