- 소프트웨어개발 프로젝트에서의 획득가치관리(EVM) 적용 사례 연구
- ㆍ 저자명
- 전성철,김자희,Jun. Sung-Chul,Kim. Ja-Hee
- ㆍ 간행물명
- 한국IT서비스학회지= Journal of the Korea society of IT services
- ㆍ 권/호정보
- 2008년|7권 3호|pp.129-144 (16 pages)
- ㆍ 발행정보
- 한국IT서비스학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
The uncertainty of software projects makes a big gap between the initial schedule/expense and the final one. Moreover, it is difficult for a project manager to reschedule and re-budget for reflecting the effects of changes in the software development. In this paper, we suggest EVM (Earned Value Management) to control the schedule and the expenses of an on-going software development project. In order to apply EVM to a software project, we consider turnkey contracts and propose the way to calculate the earned value for the software development. Finally, we illustrate our method with the case of N-company. We expect our EVM help to analyze and to predict the final schedule and the expense of a software development project.