- 관로계통 및 가압펌프장 수격에 따른 최적 안정성 확보방안
- ㆍ 저자명
- 라병필,박종호,Ra. Beyong-Pil,Park. Jong-Ho
- ㆍ 간행물명
- 유체기계저널
- ㆍ 권/호정보
- 2009년|12권 5호|pp.19-24 (6 pages)
- ㆍ 발행정보
- 유체기계공업학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
This paper is performed to find out the stability of water-hammer in pipe line and pump station that is happened when additional water needs demanded. At first, the water supply construction project is planned to supply $6,000;m^3/day$ through 17.9 km pipe line. But additional demand ($1,200;m^3/day$) happened from Cheong-ra water reservoir. In this situation, air-chamber($4;m^3$) and vacuum breaker valve(${varphi}100;mm$) are needed to prevent water-hammer. When the additional water is supplied, the existing facilities (air-chamber, vacuum breaker valve) are sufficient to alleviate shock not changing capacity alteration, judging from the airspace change and rise. Therefore, there is no problem for water-hammer by installing air-chamber($4;m^3$) and vacuum breaker valve(${varphi}100;mm$) at the top of Yeo-ju hill.