- FPSO의 선행의장률 향상을 위한 생산관리 및 공법개선 사례연구
- ㆍ 저자명
- 신성철,조종범,신기영,김수영,Shin. Sung-Chul,Cho. Jong-Burm,Shin. Ki-Young,Kim. Soo-Young
- ㆍ 간행물명
- 大韓造船學會 論文集
- ㆍ 권/호정보
- 2009년|46권 3호|pp.325-334 (10 pages)
- ㆍ 발행정보
- 대한조선학회
- ㆍ 파일정보
- 정기간행물| PDF텍스트
- ㆍ 주제분야
- 기타
Generally, functional design of FPSO has been done by the engineering firm designated by ship owner. Main equipment such as topside facility is imported from abroad. But sometimes, OFE (Owner Furnished Equipment) does not satisfy the PND (Product Need Date) of each production stage because the delivery date of OFE is not scheduled to satisfy the PND. And sometimes many loose items and equipment are complex from engineering which does not consider pre-outfitting. Main objective of this study is process improvements by maximizing pre-outfitting rate in the stage of equipping STP (Submerged Turret Production), one of main equipment on FPSO. In this study, we analyzed the factors which obstructed pre-equipping STP using the past records of FPSO projects.